Hi
I have created this function which takes the start date, end date and weekday ( where 0 is Monday and 6 is Sunday)
function countDays(dateFrom : date,dateTo : date,dow : number) do
let countDays := days(dateFrom, dateTo) + 1;
let fullDays := floor(countDays / 7);
let partDays := countDays % 7;
let addDays := (7 - weekday(dateFrom) + dow) % 7;
let extraDay := number(addDays < partDays);
fullDays + extraDay
endRegards John
-
Hello, thank you for your answer ,
I am not a code expert,
I created two date fields (From, To) and a formula with the code indicated but it displays nothing
view the photo -
-
Hi
Either Copy and paste your function into the Options / Global script definitions section and then in your formua put
countDays(DateFrom,DateTo,5)
5 tells it to count Saturdays.
Or just put this part of the code in your formula
let dow := 5;
let countDays := days(DateFrom, DateTo) + 1;
let fullDays := floor(countDays / 7);
let partDays := countDays % 7;
let addDays := (7 - weekday(dateFrom) + dow) % 7;
let extraDay := number(addDays < partDays);
fullDays + extraDayRegards John
-
perfect thank you very much john
although I could not understand the code
-
Hi
Let's take July 2021.
The number of days in the month, 31 is calculated by this line
let countDays := days(DateFrom, DateTo) + 1
There are at least 4 days for any day of the week, and this comes from dividing 31 by 7 and taking the whole number part
let fullDays := floor(countDays / 7)
There may be a 5th day. If we re-arrange the calendar we can see when that happens
We have 3 additional days, calculated by taking the modulo (the remainder) of 31 divided by 7
let partDays := countDays % 7
How many days does it take us to get from the start date to our test date
let addDays := (7 - weekday(dateFrom) + dow) % 7
If it take more days than we have available the number of days will remain at 4, but if we can get there withing the number of days availabe there will be an extra 5th day
let extraDay := number(addDays < partDays)
Now add the two together to give us our answer
fullDays + extraDay
This is the tricky line
let addDays := (7 - weekday(dateFrom) + dow) % 7
You can see how it works here
This is saying
It take 5 days to get from Monday to Saturday, it take 1 day to get from Friday to Saturday, and it takes 6 days to get from Sunday to Saturday
Regards John
-