Deriving dates
Hi all! I am looking at projects. I have different phases and duration for each of those phases, which vary per project. My first phase is definition. And my second phase (configuration) cannot start until definition has completed. I am currently using interval as the field for duration BUT ... I can't work out if there is a way to calculate the start date of my configuration based on the duration of my definition
something like... Starts Date of Definition + interval duration = start date of configuration
thanks a million!
C
1 reply
-
@celinepatterson
Yes.. sort of ... kind of .. maybe.
1. Are you concerned about weekends?
2. Is start / end inclusive or exclusive?
3. Can next phase start on the same day the prior phase ends?
4. ??????
Here is a simple snapshot.. This does not address weekends..