Deriving dates

Hi all! I am looking at projects. I have different phases and duration for each of those phases, which vary per project. My first phase is definition. And my second phase (configuration) cannot start until definition has completed. I am currently using interval as the field for duration BUT ... I can't work out if there is a way to calculate the start date of my configuration based on the duration of my definition 

something like... Starts Date of Definition + interval duration = start date of configuration 

thanks a million! 

C

1 reply

null
    • Mconneen
    • 4 yrs ago
    • Reported - view

    @celinepatterson

    Yes.. sort of ... kind of .. maybe.   

    1.  Are  you concerned about weekends? 

    2.  Is start / end inclusive or exclusive?

    3.  Can next phase start on the same day the prior phase ends? 

    4. ??????

    Here is a simple snapshot.. This does not address weekends.. 

    phaseDates

    theCode