            Need Script for transfer Dates
Hi Fred again with problems, I feel like I'm. going backwards.
On the Documents I have Two Buttons ADD Documents One by One and the other ADD ALL Documents and Works excelent.
Now I need to Copy from 'Control Deliverables' to 'News Forecast Dates' all dates Real 1 to 5 and all dates Plan 1 to 5 on OldPlan 1 to 5
On 'Control Deliverables' I have a Button name Forecast Days Re-Planning with the script.
Can you help me.
5 replies
- 
  
There are any way to do this
 - 
  
I did a test and found this works:
newR.( 'Control Deliverables_>' := me; Name_Document := me.'Name Document'; 'Forecast 1' := me.'Real 1'; 'Real 1' := me.'Real 1' )You don't need to create all those variables since you have the 'me' variable already.
Give this a try and if works for you then just expand it.
 
Content aside
- Status Answered
 - 1 yr agoLast active
 - 5Replies
 - 76Views
 - 